Development Fee, Exaction & Protest-Window Ledger

Organize impact fees, capacity charges, and exactions with SB 1036 incremental-impact offset flags, § 66007 CO deferral checks, 90-day protest and 180-day lawsuit deadlines, and CSV export.

Interactive Ledger + CSV Export · Runs Locally

Track Development Fees, SB 1036 Offsets & § 66020 Protest Deadlines

Organize impact fees, utility capacity charges, Quimby fees, and school/district exactions. Automatically flag SB 1036 (effective January 1, 2027) incremental-impact offsets, check Gov. Code § 66007 residential deferral rules, compute 90-day protest / 180-day judicial deadlines, and export cleanly to CSV.

Discuss Fee Strategy
Total Gross Fees$417,000.003 tracked item(s)
Existing-Use Offsets$53,000.002 SB 1036 flag(s)
Net Modeled Exposure$364,000.00Verify fee schedules with agency & counsel
Earliest 90-Day Protest2027-02-13180-day action: 2027-05-14
Line 01 · Net $150,000.00
Demolition / Change of Use
§ 66007 Timing Note — Aligned with Gov. Code § 66007(a) final-inspection / certificate-of-occupancy deferral baseline.
§ 66020 Deadlines — 90-day protest: 2027-02-13 | 180-day action: 2027-05-14
SB 1036 Incremental-Impact Offset Flag — SB 1036 (Stats. 2026, ch. 54, eff. Jan. 1, 2027 — Gov. Code, § 66001): requires impact fees on projects demolishing or changing an existing use to be offset to the incremental impact on public facilities.
Line 02 · Net $74,000.00
Demolition / Change of Use
§ 66007 Timing Note — Gov. Code § 66007(a) (as amended by SB 499, Stats. 2025, ch. 543): utility service fees/charges related to connections may be collected at service application up to actual connection cost.
§ 66020 Deadlines — 90-day protest: 2027-02-13 | 180-day action: 2027-05-14
SB 1036 Incremental-Impact Offset Flag — SB 1036 (Stats. 2026, ch. 54, eff. Jan. 1, 2027 — Gov. Code, § 66013(j)): water/sewer capacity charges for a change in existing connection capacity must reflect only the incremental change in capacity (no refund/transfer credit if existing capacity exceeds proposed).
Line 03 · Net $140,000.00
Demolition / Change of Use
§ 66007 Timing Note — Gov. Code § 66007(a)–(b): residential public-improvement fees generally defer to final inspection or CO unless the agency made § 66007(b)(1) appropriation/schedule or reimbursement findings.
§ 66020 Deadlines — Add imposition/notice date to compute 90-day protest & 180-day judicial deadlines.

Further Reading

Acquiring Entitled Land: A Framework for Reviewing the Approval Record

A practical method for testing what an approval covers, what remains open, and what could affect reliance or implementation.

Due Diligence for Access, Utilities, and Off-Site Improvements

Test legal rights, physical capacity, provider conditions, required improvements, funding obligations, phasing assumptions, and the evidence supporting delivery.

Related Services

High-resolution architectural floorplans, aluminum drafting scale, and mechanical pencil on a studio table.

Project Feasibility & Due Diligence

Establish the operative record, test the assumptions behind the development thesis, and assign the questions that could change the transaction or project path.

Explore Service
Palm-lined California coastal residential corridor descending toward the Pacific Ocean.

Entitlements & Approvals

Define the approval path, align the project team, coordinate agency review, and keep complex decisions moving.

Explore Service

Next Steps

Apply This Framework to a Live California Project

Share your current project stage, operative approval record, and upcoming schedule or filing gate to evaluate a scoped advisory workplan.

Schedule a Consultation