Tentative Map Life & SB 1169 Horizon Calculator

Model pre-2027 vs. post-SB 1169 tentative tract map timelines, parcel-map distinctions, phased off-site extensions, discretionary caps, moratoria, litigation stays, and DA coterminous life locally in your browser.

Interactive Calculator · Runs Locally in Your Browser

Model Pre-2027 vs. Post-SB 1169 Map Horizons

Test how SB 1169 (Stats. 2026, ch. 423, effective January 1, 2027) interacts with tentative tract maps versus parcel maps, local ordinance extensions, phased off-site improvements, stays, and development agreements. Nothing entered here leaves your browser.

Discuss Map Horizon

1. Map & Extension Parameters

Tract maps: up to 24 mo. pre-2027; up to 36 mo. under SB 1169.

Statutory cap: 6 years total (§ 66452.6(e) / § 66463.5(c)).

Each adds +48 mo. (10-yr cap) when off-site threshold is met.

Up to 60 months (§ 66452.6(b)).

Up to 60 months with agency stay approval (§ 66452.6(c)).

Phased Off-Site Improvement Threshold
Recorded Development Agreement

2. Modeled Horizon & SB 1169 Comparison

Pre-2027 Baseline2028-06-15Base (24 + 12 mo.): 2028-06-15
Post-SB 1169 Horizon (2027+)2030-06-15Base (48 + 12 mo.): 2030-06-15
SB 1169 Applicability Check — Because this modeled tentative tract map remains unexpired as of December 31, 2026, Gov. Code § 66452.6(a)(1)(B) (as amended by SB 1169, Stats. 2026, ch. 423, eff. Jan. 1, 2027) applies the 48-month initial term and up to 36-month local-ordinance allowance. Confirm exact agency calculation and local ordinance language.

Agency & Counsel Verification Checklist

  • Obtain the signed resolution or ordinance showing the exact tentative-map approval or conditional-approval date (not staff-report date).
  • Confirm local subdivision ordinance automatic initial-term additions and whether the jurisdiction adopted additional months following SB 1169.
  • Collect written approval resolutions for every prior discretionary extension and verify total discretionary years remaining under the 6-year statutory cap.
  • Compare current architectural/product plans against the approved vesting tentative map to confirm substantial compliance before relying on vested ordinances (§ 66498.1).
  • Confirm timely filing protocol with the city engineer or county surveyor well ahead of expiration — filing a discretionary extension application before expiration triggers a 60-day automatic extension pending action.

Statutory Anchors

  • Gov. Code, § 66452.6(a)(1), (e) — Tentative tract map life (pre-2027: 24 mo. + up to 24 mo. local; effective Jan. 1, 2027 per SB 1169, Stats. 2026, ch. 423: 48 mo. + up to 36 mo. local for maps unexpired on Dec. 31, 2026; up to 6 yrs discretionary extensions).
  • Gov. Code, § 66452.6(a)(1)–(2) — Phased final-map off-site public-improvement extensions (+48 months per phased final map, capped at 10 years from approval; statutory base $236,790 adjusted annually March 1 by State Allocation Board Class B construction index).
  • Gov. Code, § 66452.6(b)–(c) — Development moratorium tolling (up to 5 years; 120-day post-moratorium floor) and agency-approved litigation stay (up to 5 years; agency acts within 40 days of stay application).
  • Gov. Code, §§ 66498.1, 66498.5 — Vesting tentative map rights expire if a final map is not approved before map expiration; post-final-map vested rights run under § 66498.5(b)–(d).
  • Gov. Code, § 66452.6(d) / § 66463.5(b) — Timely delivery of the final/parcel map to the county surveyor or city engineer before expiration preserves subsequent agency processing and recordation.

Further Reading

Vesting Tentative Maps: A Project-Reliance Framework for Filing, Approval, Final Mapping, and Permit Delivery

Identify the rules carried by the vesting tentative map, preserve the applicable baseline, coordinate final maps and permits, and keep the reliance period visible.

Acquiring Entitled Land: A Framework for Reviewing the Approval Record

A practical method for testing what an approval covers, what remains open, and what could affect reliance or implementation.

Related Services

High-resolution architectural floorplans, aluminum drafting scale, and mechanical pencil on a studio table.

Subdivision & Land Development

Align project feasibility, subdivision strategy, entitlements, agency coordination, and implementation from the outset.

Explore Service
High-resolution architectural floorplans, aluminum drafting scale, and mechanical pencil on a studio table.

Project Feasibility & Due Diligence

Establish the operative record, test the assumptions behind the development thesis, and assign the questions that could change the transaction or project path.

Explore Service

Next Steps

Apply This Framework to a Live California Project

Share your current project stage, operative approval record, and upcoming schedule or filing gate to evaluate a scoped advisory workplan.