Permit Streamlining & SB 330 Submittal Clock Modeler

Calculate SB 330 180-day full-application and 90-day cure deadlines, 30-day § 65943 completeness cycles, 30/60/90/180-day post-CEQA approval windows, >=20% revision triggers, and the 5-hearing cap.

Interactive Modeler · Runs Locally in Your Browser

Model Permit Streamlining & SB 330 Clocks

Calculate SB 330 180-day full-application and 90-day incompleteness cure deadlines, 30-day § 65943 completeness windows, 30/60/90/180-day § 65950 decision clocks (including AB 130 urban infill exemptions), ≥20% vesting resubmittal alerts, and the 5-hearing cap.

Discuss Submittal Clock

1. Submittal Dates & Hearing Track

Project Classification

≥20% revision (excl. density bonus) triggers § 65941.1(d) resubmittal.

Gov. Code § 65905.5 caps qualifying housing projects at 5 hearings.

2. Statutory Clocks & Guardrail Status

PSA Decision Window60 DaysGov. Code, § 65950(a)(4)
SB 330 Hearing Cap2 / 5Gov. Code, § 65905.5
Hearing Posture — 2 of 5 allowable hearings used (3 remaining under Gov. Code, § 65905.5(a); continuances count as hearings).

Modeled Milestone Schedule

  • Preliminary Fee & Exaction Estimate (If Requested)
    2026-12-11

    30 business days (excludes weekends; check local holidays) (Gov. Code, § 65941.1(b)(1)) — Informational good-faith estimate only; request special-district/school fee schedules separately.

  • SB 330 Full Development Application Submittal Deadline
    2027-04-30

    180 calendar days from preliminary application (Gov. Code, § 65941.1(e)(1)) — Missing the 180-day window forfeits preliminary-application vesting of ordinances, policies, and standards.

  • Agency Written Completeness Determination Deadline
    2027-03-17

    30 calendar days from application submittal (Gov. Code, § 65943(a)) — Agency must issue an exhaustive checklist-bound incompleteness list within 30 calendar days; if omitted (and application states it is for a development permit), the application is deemed complete.

  • Permit Streamlining Act Approval / Disapproval Window
    2027-09-13

    60 calendar days (From adoption of Negative Declaration / Mitigated Negative Declaration) (Gov. Code, § 65950(a)(4)) — Subject to written mutual extension under Gov. Code § 65957; verify any statutory deemed-approval notice procedures with counsel.

Submittal-Control Guardrails

  • Confirm the development application explicitly states it is an application for a development permit so the 30-day § 65943 deemed-complete rule attaches.
  • Lock every submittal item against the agency's published § 65940 checklist; flag any agency comment requesting information outside the published checklist or added after the first incompleteness letter.
  • Monitor residential unit count and Title 24 building square footage revisions carefully: a >=20% change (excluding density-bonus increases) triggers mandatory SB 330 preliminary-application resubmittal under § 65941.1(d).
  • Track every planning commission, design review, council, appeal, workshop, and continued hearing against the 5-hearing limit (§ 65905.5).
  • Archive dated written delivery receipts for every preliminary submittal, full submittal, agency completeness letter, and resubmittal in the Data-Room Index.

Further Reading

From Pre-Application to Complete Application: A Submission-Control Framework

Build a controlled entitlement package across agency checklists, project facts, technical inputs, statutory milestones, completeness comments, and resubmittals.

Related Services

Palm-lined California coastal residential corridor descending toward the Pacific Ocean.

Entitlements & Approvals

Define the approval path, align the project team, coordinate agency review, and keep complex decisions moving.

Explore Service
Laguna Beach coastal hillside community illuminated by late-afternoon California sunlight.

CEQA & Environmental Planning

Coordinate project decisions, technical work, agency review, and entitlement timing through one integrated CEQA and environmental-planning workplan.

Explore Service

Next Steps

Apply This Framework to a Live California Project

Share your current project stage, operative approval record, and upcoming schedule or filing gate to evaluate a scoped advisory workplan.

Schedule a Consultation